Structures

 

 

 

LIST OF PROJECTS

 

 

 

 

 

 

 

 

 

Project

Name of Project

Name of Client

Name of consultant

Type of work

Contract Amount in MNDhs

Commencement Completion

1. AD404

Rehabilitation & Widening of Abu Dhabi - Dubai Road, Contract No. 2

Public Works Dept. Abu Dhabi

Parkman Consultants Limited

18 km of 4-Lane Highway and One Interchange at Al Reef Palace

160.74

24/04/1995 30/10/1997

2. AD407

Bridge over Truck Road between ME11 & ME12 at Mussafah

Abu Dhabi Municipality

Freeman Fox International

Bridge work and Link Roads, and 7 No. Gas Pipeline Culverts

53.00

05/06/1997 30/06/1999

3. AD445

Construction of Bridge at Officers City and between Two Bridges City Contract 999

Abu Dhabi Municipality

Frederic R Harris Inc

Construction of an Underpass Dual Carriageway traversing the Mussafah Road/Abu Dhabi International Airport Expressway, and a steel arch bridge over the recreational canal between the City between 2 bridges & Police Officers City

53.05

23/11/2002 14/07/2004

4. AD440

Improvements to Clock Tower Roundabout at Al Ain Time Square.

Al Ain Municipality

Scott Wilson Kirkpatrick & Co

Construction of Clock Tower Monument structure and 25m diameter Clock installation as well as reconfiguration of traffic junction at Time Square.

28.68

01/10/2002 30/04/2005

5. AD429

Sheikh Zayed Bridge Contract No. 2

Works Department

Rendel Palmer & Tritton

290m Long (5 Span) Twin Bridge with Prestressed Concrete Voided Deck slab and 300m Long 6 Span single Bridge with Prestressed Concrete voided Deck Slab, Widening/ Reconstruction of approach roads and associated utilities work

106.96

19/01/2002 26/10/2005

6. AD466

Suspended works in Contract 2 of Sheikh Zayed Bridge, Contract 2A

Department of Municipal Affairs - Municipality of Abu Dhabi City

High Point Rendel

Construction of MSE Wall, Embankment Road works and associated Services to Tie-in with existing structure, Extension of Minor Road and Finishing works of Lighting Control Building

21.70

07/09/2008 07/07/2009

7. AD465

ADNEC - New Exhibition Facilities- Phase-2, Package No.EX4010 - ADNEC Package-2, Road Works and Ramp Package

Abu Dhabi National Exhibitions Company (ADNEC)

Project Manager:Mace International, and Engineers: RMJM /Hyder Consulting

Construction of Road Works & Traffic Management.  Widening of Karama Street and Street 5, Resurfacing Footpaths, Storm Water and Street Lighting. Construction of 300m Ramp and Bridge Access to Multistorey Car Park.

83.00 

01/07/2008 31/03/2010

8. AD485 

Al Ain Wildlife Park & Resort Project: Design and Build Contract of Main Entry, Parking, Linear Park and Periphery Themed Retaining Wall 

Zoo & Aquarium Public Institution in Al Ain

Hyder Consulting

Construction of Lighting Concrete Retaining Wall and Mockrock Works 

16.70 

21/07/2010
30/11/2011

 

9. AD492

Barakah Nuclear Power Plant Project Retaining Wall and UCT Works

HYUNDAI E&C and SAMSUNG C&T Joint Venture (HSJV).

Korea Electric Power Corporation (KEPCO)

Retaining Wall and Underground Common Tunnel Construction Work.

23.43

07/11/2011
07/09/2013

10. AD507

Barakah Nuclear Power Plant – Circulating Water Intake Structure, Units 1 to 4

Hyundai Engg & Construction

Hyundai

Construct reinforced concrete (RC 89710 m3) for the Circulating Water Intake Structures for Units 1 to 4

219.90

04/05/2013

03/02/2017

11. AD517

Barakah Nuclear Power Plant /UAE – Circulating Water Intake/Discharge Conduits within the Footprints of Units 3 and 4.

Hyundai E&C and Samsung C&T Joint Venture (HSJV)

HSJV

Construction of R.C. Circulating water Intake/ Discharge conduits (Culverts) for Barakah Nuclear Power units 3 & 4 (approx.. 137,000 m3 concrete) – 1400m length of Multicell Culvert comprising of 4x4m           X-section cells 2560 LM and 8x8m cells 3274 LM. Hydrostatic testing of each conduit /commissioning.

270.24

07/02/2014

30/09/2016